Use of an activate-able scraper in a drilling or cleanout BHA
02 August 2018 Dear all,Here's another item that keeps cropping up.
A well re-entry is being planned. The well has was temporarily-suspended with a cement plug inside 11¾" liner and the shoetrack had not been drilled out.
The re-entry plan requires a USIT/CBL to be conducted to investigate the bond outside the liner.
Due to drilling out a cement plug, and - possibly part of the shoetrack - the wireline company has requested that we scrape the casing. The team are looking at various options, which include:
- Incorporate a 'drilling scraper' in the BHA (ODfjell's DrillRdillo comes to mind): these are run in the 'collapsed' state and after drilling is finished, they are activated (ball) and then the casing can be scraped.
- Incorporate a 'non-rotating' scraper in the BHA (MI-Swaco's Razorback comes to mind), and anticpating that the drilling bit/mill will grind the cement up small enough so as not to cause a problem
- Don't bother running a scraper at all (after all scrapers are hardly ever run before bond logs)
Thankyou
Dave
_____
Note added later: The reason that we need to know about the cement bond is because the contingency plan (if we cannot re-use the old hole below the liner) is to conduct a cased-hole sidetrack.
6 Answer(s)
PLEASE LOGIN OR SIGN UP TO JOIN THE DISCUSSION
Support Spread
We need the support of our members to keep our forum online. If you find the information on spread useful please consider a donation
Posted by
Related Discussions
Moving rigs at deep raft
Securing Drillstring
Pre-making BHA's Onshore
Removing Trapped Air From Subsea Wells
Overside Working Requirements