BOP Removal Un Perforated Well

05 April 2023

Guys,

I have a land well un perforated, low pressure.

Casing and Liner set, cemented and tested, logs show good cement behind casing. the well has been suspended for a time period with 2 cement plugs.

Plugs were drilled out and a corrosion log was performed on the liner which showed excellent condition.

Wellbore is full of Completion Fluid 500 psi over reservoir pressure.

A tubing spool replacement is required which will involve nippling down and nippling up BOPs.

Can I class the cemented casing and liner as one barrier and the fluid as the second? Is a plug also required? is it a nice to have? is it a case by case decision?

Seems to be a bit of a grey area

Please your thoughts gents.

10 Answer(s)

Support Spread

We need the support of our members to keep our forum online. If you find the information on spread useful please consider a donation

donate