Suspending Drilled Wells Mid-way
24 August 2009 Was wondering what best practice was for suspending wells mid-way through drilling. We [BHPBilliton Australia] have a two-barrier policy. The result is we use two RTTS packers. This is time consuming and can be risky if there is any trouble with the packers.Look forward to hearing what others are doing
8 Answer(s)