BOP Removal Un Perforated Well

Guys,

I have a land well un perforated, low pressure.

Casing and Liner set, cemented and tested, logs show good cement behind casing. the well has been suspended for a time period with 2 cement plugs.

Plugs were drilled out and a corrosion log was performed on the liner which showed excellent condition.

Wellbore is full of Completion Fluid 500 psi over reservoir pressure.

A tubing spool replacement is required which will involve nippling down and nippling up BOPs.

Can I class the cemented casing and liner as one barrier and the fluid as the second? Is a plug also required? is it a nice to have? is it a case by case decision?

Seems to be a bit of a grey area

Please your thoughts gents.