Abandonment of MLS Well with Possible live 9 5/8/7" Annulus
28 March 2011 I´m piecing together a programme for the abandonment work of a well which was drilled in the Dutch Waters in 1982 and info is sparse. This is a Cameron MLS (Torque Set?) and I am still trying to establish with them the correct suspension caps and wellheads.Because it has been down there since 1982 there is a requirement to cover all contingencies for this well, as in its history the 9 5/8 / 7” annulus was ”˜live´ after a bad cement job and was bullhead dead with heavy WBM. There is a possibility it maybe ”˜live´ below the sealed caps. There was a mechanical plug and cement plug placed above the perfs in the 7" casing. The 7" casing is hung in the MLS.
The plan is a 30" conductor.
Removal of the 20” (non-sealing cap).
A surface well head system to allow for the tie ins of the above onto 21/1/4” BOP and for 20”
Removal of 13 3/8 & 9 5/8 (sealed caps with BPV). Possible trapped pressure below the caps and damaged o BPV not functioning. (J-type sealed retrieving too with stinger)
Tie-in of 20”/13 3/8 & 9 5/8 to mudline and of the 13 3/8 / 9 5/8 on 13 5/8 BOP.
As anyone been involved on similar best/worst case with 'live' 9 5/8/7" annulus below the 9 5/8 cap. Arranging contingency for having to retrieve the cap with damaged BPV that may or may not seal.
Thanks for your input.
Dave
9 Answer(s)
PLEASE LOGIN OR SIGN UP TO JOIN THE DISCUSSION
Support Spread
We need the support of our members to keep our forum online. If you find the information on spread useful please consider a donation
Posted by
Related Discussions
Drilling 8 1/2" hole out of 20" shoe
37" HoleOpeners
Flexjoint wearbuushings
Clearing site for landrigs
Thru tubing fishing